Question 1
Which of the following is one of the four current SAFe Core Values?
Show answer & explanation
Correct answer: D - Transparency
10 free, exam-style SAFe Scrum Master (SSM) (SSM) practice questions with answers and explanations. No signup required. Work through them below, then take the full free SSM practice test to study every exam domain.
The SSM exam has 45 questions and runs 1 hour 30 minutes.
These 10 free SSM questions are organized by exam domain, so you can see how each part of the SAFe Scrum Master (SSM) blueprint is tested. Reveal the answer and explanation under each question.
Which of the following is one of the four current SAFe Core Values?
Correct answer: D - Transparency
A team makes its work-in-process visible on a board and caps how many items can be in each column at once. Which SAFe Lean-Agile principle is the team applying?
Correct answer: B - Make value flow without interruptions
During an iteration, a team member repeatedly misses commitments because another department keeps pulling them into unplanned work. What is the Scrum Master's BEST first action?
Correct answer: A - Coach the team to surface and address the impediment through its own events
A new team member asks the Scrum Master directly how to solve a technical design problem the team is debating. Which response BEST reflects a coaching stance rather than mentoring?
Correct answer: A - "What options has the team weighed, and what trade-offs do you see?"
How does the role of a Scrum Master on an Agile Release Train differ MOST from that of a Scrum Master on a single independent Scrum team?
Correct answer: C - The SAFe Scrum Master also has responsibilities toward the other teams on the train
A team finishes an 8-point story and a 2-point story, and completes about half of a 5-point story by the end of the iteration. What velocity should be recorded for this iteration?
Correct answer: D - 10
Which statement BEST describes the difference between the Iteration Review and the Iteration Retrospective?
Correct answer: A - The review inspects the product with stakeholders; the retrospective inspects the process
At the end of PI Planning, the ART's confidence vote produces an average of 2.4 on the fist-of-five scale. What should happen next?
Correct answer: B - The teams rework the plan until adequate confidence is reached
During PI Planning, a team identifies a dependency risk and decides one engineer will take responsibility for tracking and managing it going forward. Using ROAM, how is this risk categorized?
Correct answer: B - Owned
The Inspect & Adapt event is made up of three parts. Which part occurs FIRST?
Correct answer: D - The PI System Demo
Practice hundreds more SSM questions with instant scoring, weak-area drills, and full exam simulations.